SDC Installment Payment Plan
As an incentive to investors and developers,
the City of Molalla has adopted an ordinance allowing system
development charges to be deferred or paid in installments.
When the total of city system development
charges due exceeds $50,000, the city manager may approve deferred
payments until such time as an occupancy permit is issued. An
occupancy permit may not be issued until all system development
charges are paid.
When the total of city system development
charges due $100,000, the developer may choose to make installment
payments equal to one fifth of the amount owed, on an annual basis,
for a period not to exceed five years, with interest accruing on the
balance owed at a rate established by resolution of the Council.
An occupancy permit may not be issued until the person
responsible for payment of the system development charges executes
an installment payment agreement with the city.
In the event a developer elects to pay SDCs in
installments as provided above, the City shall cause a lien to be
placed upon the property in an amount equal to the balance owed,
including interest, until payment has been received in full.
LAND USE FEE
SCHEDULE
| LAND USE REVIEW |
PROC
TYPE |
LAND USE
REVIEW FEE |
HEARING
FEE |
TOTAL
FEE |
APPEAL
FEE |
| Bear Creek Easement |
I |
$300.00 |
N/A |
$300.00 |
$150.00 |
| Condominium Project 6 or fewer |
I |
$100 |
N/A |
$100.00 |
$50.00 |
| Condominium Project 7 or more |
IV |
$900 + $40 Per Unit |
$600.00 |
Total of Two Fees |
Half of Total |
| Demolition - Accessory Buildings |
I |
$50.00 |
N/A |
$50.00 |
$25.00 |
| Demolition - Building |
I |
$100.00 |
N/A |
$100.00 |
$50.00 |
| Excavation & Fill |
I |
$200.00 |
N/A |
$200.00 |
$100.00 |
| Final Plat |
I |
$300.00 |
N/A |
$300.00 |
$150.00 |
| Hardship Permit for Travel Trailer |
I |
$250.00 |
N/A |
$250.00 |
$125.00 |
| Lot Line Adjustment |
I |
$200.00 |
N/A |
$200.00 |
$100.00 |
| Master Plan Review |
I |
$1,000.00 |
N/A |
$1,000.00 |
$500.00 |
| Non-Conforming Use |
I |
$800.00 |
N/A |
$800.00 |
$400.00 |
| Pre-Application Conference |
I |
5% OF FILING FEE |
N/A |
TOTAL OF TWO |
HALF OF TOTAL FEE |
| Road Naming |
I |
$100.00 |
N/A |
$100.00 |
$50.00 |
| Signs |
I |
$50.00 |
N/A |
$50.00 |
$25.00 |
| Temporary Permit |
I |
$250.00 |
N/A |
$250.00 |
$125.00 |
| Adjustment - Type I |
I |
$350.00 |
N/A |
$350.00 |
$175.00 |
| Adjustment - Type II |
II |
$700.00 |
N/A |
$700.00 |
$350.00 |
| Design Review |
|
|
|
|
|
| Valuation of $0 to $10,000 |
I |
$200.00 |
N/A |
$200.00 |
$100.00 |
| Valuation of $10,001 to $25,000 |
II |
$400.00 |
N/A |
$400.00 |
$200.00 |
| Valuation of $25,001 to $50,000 |
II |
$600.00 |
N/A |
$600.00 |
$200.00 |
| Valuation of $50,001 to $100,000 |
II |
$1,000.00 |
N/A |
$1,000.00 |
$200.00 |
| Valuation of $100,001 to $500,000 |
II |
$1,500.00 |
N/A |
$1,500.00 |
$200.00 |
| Valuation of $500,001 to $1,000,000 |
II |
$2,500.00 |
N/A |
$2,500.00 |
$200.00 |
| Valuation over $1,000,000 |
II |
$3,500.00 |
N/A |
$3,500.00 |
$200.00 |
| Partition |
II |
$1,000.00 |
N/A |
$1,000.00 |
$200.00 |
| Conditional Use |
III |
$1,000.00 |
$700.00 |
$1,700.00 |
$850.00 |
| Preliminary Plat |
III |
$1,000.00 + $50 PER LOT |
$700.00 |
TOTAL OF TWO |
HALF OF TOTAL FEE |
| Variance |
III |
$300.00 |
$700.00 |
$1,000.00 |
$500.00 |
| Comprehensive Plan Amendment |
IV |
$2,000.00 |
$600.00 |
$2,600.00 |
$1,300.00 |
| Conditional Use Mining |
IV |
$500.00 |
$600.00 |
$1,100.00 |
$550.00 |
| Annexation |
IV |
$1,500.00 |
$600.00 |
$2,100.00 |
$1,050.00 |
| Zone Change |
IV |
$1,100.00 |
$600.00 |
$1,700.00 |
$850.00 |
| UGB Amendment |
IV |
$1,800.00 |
$600.00 |
$2,400.00 |
$1,200.00 |
| Demolition - Landmarks, Inventoried |
IV |
$1,000.00 |
$600.00 |
$1,600.00 |
$800.00 |
| ELD (Expedited Land Division) |
IV |
$1,000.00 + $50 PER LOT |
$1,500.00 |
TOTAL OF TWO |
HALF OF TWO |
| Zoning Fee |
|
| Single-Family Residential Addition |
$50.00 |
| Single-Family Residential (New
Construction) |
$75.00 |
| Accessory Dwelling Units |
$35.00 |
| Duplex |
$100.00 |
| Multi-Family Residential |
$125.00 plus $10 per unit |
| Commercial / Industrial |
10% of Design Review or Minimum $25.00 |
| City Administration Fee |
6% of Total Cost of a Permit minus State
Surcharge |
* All appeals will incur a hearings cost. Staff will require a
deposit of $600.00 and will not continue with the process until
additional monies are paid once staff has exhausted the original
$600.00 fee.
*Additional costs may be collected in the case the expenses exceed
the amount collected on all applications.
|